| Item |
Required Information |
Notes / Suggestions |
| A. Contacts |
- Provide name, title, email address, fax and phone numbers of a key contact
for inquiries regarding the submission contents.
- Provide current contact information for the institute director, principal
investigator (lab supervisor), facilities manager, and biosafety officer.
|
|
| B. Program Intent |
- Give a brief overview of the agents to be used and procedures to be
followed in your facility, as well as the general goal/purpose of the
work.
- Provide a list of pathogens manipulated and/or stored in the facility.
- Provide a list of animal species manipulated in the facility.
- A program change request must be submitted to this office before any new
pathogen is introduced in the facility.
- At any time there is a significant change in procedures, you are required
to inform this office immediately.
|
- Information to include: maximum volumes of infectious materials to be
worked with, identification of any procedures that may produce aerosols, etc.
|
| C. Drawings and Specifications |
- All "as built" drawings for the facility including architectural,
mechanical (HVAC, plumbing,
piping, drainage), electrical, and control schematics. If "as built"
drawings are not available, tender or construction drawings with change orders
are acceptable.
- Specifications as listed above including sequence of operations.
|
- Drawings for associate structures/services are also required, for example:
biowaste system, incinerator, etc.
- Indicate the containment barrier on all
drawings.
|
| D. Verification & Performance Testing |
- For each required test or verification, describe the test procedure,
acceptance criteria, observations, results, pass/fail decision, names, dates,
signatures, witnesses and corrective measures required. Testing must have been
performed during the last 12 months.
|
|
| 1. Room Integrity |
- Visually and with a smoke pencil, or other visual aid, confirm the
integrity of all penetrations and seals on the containment perimeter (include
service penetrations and seals around doors, windows, autoclaves and dunk
tanks).
- Visually inspect floors, walls, and ceiling for cracks, chips or wear, and
verify integrity of wall/floor and wall/ceiling joints.
- List all defects and corrective measures and re-test results.
|
- List by room, either in a table or schematic or by elevation of the
facility.
|
| 2. Communication Devices |
- Provide a list and a statement as to how they were verified as operational
(phone, intercom, radio, video, etc.).
|
- Communication should be maintained with minimum interruption during power
outage.
|
| 3. Door Interlocks |
- Indicate combination of doors which are interlocked (e.g. door A with door B, door B with door A and
C).
- Verify operation of doors and applicable interlocks to ensure that doors
cannot be opened simultaneously.
- Verify that emergency egress overrides the interlocks.
- For facilities that do not have physically-interlocked doors, please
confirm that procedures are in place to ensure that no critical combinations of
doors can be opened simultaneously.
|
- Provide a plan of the facility and surroundings with clearly labelled doors
(i.e. each individual door is uniquely
identified).
|
| 4. Access Control and Security Devices |
- List access control and security devices on all entry points to the
containment area (change rooms, anterooms, pass through, etc.).
- Provide verification that they operate as intended.
- If there is a door on the containment perimeter (directly between the lab
and a clean area/corridor), please indicate if that door is sealed and how
access is controlled.
|
- Verify that a correct code/card works and also that an incorrect code/card
will not work.
|
| 5. Demonstration of Inward Directional Airflow (during
normal operation) |
- Inward directional airflow to be visually demonstrated at all critical
doors (e.g. by holding a smoke pencil, or
other visual aid, at each door leading to adjacent area).
- Include a labeled floor plan (letter/legal sized format) with arrows
indicating the directional airflow for each door tested.
|
- Air must flow towards areas of higher containment.
|
| 6. Autoclaves & Disinfection Systems |
- Autoclaves to be verified for operation as specified and to be
microbiologically tested using representative loads.
- Include the time/temperature criteria required for your specific
agent/waste.
- Include a description of the different types of loads to be run and a short
description of the load test procedure (e.g.
laundry, solid waste, liquid waste, etc.).
- Include a time/temp chart and biological indicator test results for each
load test performed. Positive control results must be included (from the same
lot#).
- Provide verification that interlocking doors or visual/audible alarms are
functioning as intended.
- All disinfection systems (e.g. dunk tanks,
fumigation chambers, etc.) to be verified to
operate as intended and microbiologically tested using representative
loads.
|
- Generally, for technologies based on heat, Geobacillus
stearothermophilus spores are adequate and, for technologies based on
chemicals, Bacillus subtilis spores are used.
- Resistance of test organism must be representative
of organisms likely to be encountered.
|
| 7. Backflow Preventers |
- Provide a list of all backflow preventers associated with the lab
(including type, general location, and purpose).
- Water supply backflow preventers must be tested in accordance with CAN/CSA-B64.10-07/B64.10.1-07:
Manual for the Selection and Installation of Backflow Prevention
Devices/Manual for the Maintenance and Field Testing of Backflow Prevention
Devices (2007).
- Provide backflow preventers test certificates.
- Provide the name and certification number of the tester.
- Backflow prevention for other services (e.g. gases) to be verified to ensure that the system
will operate as specified.
|
- This helps ensure all backflow preventers are accounted for.
|
| 8. Emergency Generator |
- Provide a load test report.
- Verify that all critical systems are on emergency power (including, but not
limited to, controls, fans, security, critical equipment, phones, effluent
treatment, etc.).
- Previous monthly test report is acceptable.
|
- Load testing results should verify that the generator can pick up and carry
the load if required. When live load testing is not possible, simulated load
testing is acceptable.
|
| 9. Effluent Treatment*
* See section 3.5.6 in Containment Standards for Facilities Handling
Aquatic Animal Pathogens
*Not required for AQC3
in vitro facilities
|
- The system and run criteria are to be validated by microbiological
challenge. Ideally, the methodology should be discussed with the Office of
Biohazard Containment and Safety, CFIA.
- Briefly describe the run criteria for the specific agent/waste in use.
- Describe the microbiological challenge and verification procedures.
- Provide trending charts, test reports, digital printouts and other data as
pertinent.
- Drains and associated piping leading to effluent treatment systems
(including associated vent lines) to be tested in accordance with National
Plumbing Code of Canada, section 3.6 (1995); Canadian Commission on
Building and Fire Codes, National Research Council Canada. Pressure for air
test on drainage system shall be a factor of safety beyond standard code
requirements of 35 kPa (e.g. 2 x code).
- A backup effluent decontamination system or holding system must be in
place.
- Alarm system to be provided to indicate failure of effluent treatment
system.
|
- Effluent treatment systems that are not completely closed and contained
must be housed in a room designed to the same containment level as the
containment facility.
- Effluent treatment system must be equipped with a
sludge/sediment removal/collection system.
|
| 10. Biological Safety Cabinets |
- Provide a list of all BSCs associated with the lab plus
the test certificate for each.
- Each BSC test
certificate must contain the following information:
- type of cabinet and type of exhaust connection;
- standard to which the cabinet was tested and the qualifications of the
tester;
- statement as to whether the HEPA filter was scanned or
probed, and the pass/fail criteria;
- when NSF 49 is
not applicable, the particle penetration given as a percentage of the upstream
challenge must be provided;
- indication of any repairs and retest results;
- downflow and inflow (exhaust) measurements and acceptable ranges specific
for the model;
- alarm test results - airflow tests, failure alarm test; and
- test of airflow patterns within the cabinet.
- Class III BSC to be tested in accordance with
BS EN 12469:2000: Biotechnology- Performance criteria for microbiological
safety cabinets (2000); British Standards Institute, and Laboratory
Safety Monograph: A Supplement to NIH Guidelines for Recombinant
DNA Research (1979);
National Cancer Institute Office of Research Safety and the Special Committee
of Safety and Health Experts. Acceptance criteria: measured leakage from any
point in the cabinet shall not exceed a leak rate of 10 X 10-7 cc/sec at 750 Pa (3 inches w.g.).
- Provide the calibration certificates for the equipment used for the
verification.
|
- This helps ensure all BSCs are accounted for.
- Class II B2 Puff back: the
time from the moment of alarm detection of failure to the moment of air reflux
from the cabinet should be known. If not carried out when installed, testing
and adjustment of the cabinet alarm should be done as to give the earliest
warning possible to the user and maximize the amount of time before the puff
back occurs.
|
| 11. Control Systems/Fail-Safe Operation |
- Submit a report for each failure scenario performed.
- Failures to be simulated include:
- exhaust fan failure;
- supply fan failure;
- power failure (if not possible, provide reason why);
- effluent treatment system failure;
- additional failures (as appropriate) for the particular facility (e.g. class II B2 BSC exhaust failure, control panel
failure, etc.).
- For each failure, verify that:
- room positive pressurization is prevented;
- inward directional airflow is maintained at all critical doors (verify the
airflow by smoke pencil, or other visual aid); and
- audible and visual alarms function correctly
- Each report to contain:
- description of the failure protocol and the control/HVAC systems'
expected response;
- indication as to whether or not the system responded as expected;
- results of verification and maintenance of inward directional airflow;
and
- alarm results.
- Report and describe the investigation of any system failures (e.g. reversed airflow, fan interlock failure) as
well as corrective measures taken.
- Submit control sequence of operation.
|
- In some circumstances brief airflow reversals (of a few seconds) may be
acceptable - consult with this office.
- Audible alarms should also to be tested for the
capability to detect positive pressurization.
- A simple way to depict airflow results is with a
labelled plan using arrows to indicate the directional airflow at each critical
door tested.
- Graphs and trend logs for failure scenarios are
helpful and desirable.
|
| E. Biosafety Manual
Note: the Biosafety Manual, which may consist of a
collection of Standard Operating Procedures (SOPs), is a critical part of the
certification documentation. Please realize that fulfilling the requirements of
this section entails a substantial amount of work and detail.
Do not leave this section until project completion.
An example of items to be address in each SOP are:
- Purpose
- References
- Personnel/Responsibility
- Glossary/Definitions
- Equipment and Material Required
- Safety
- Policy
- Detailed Instructions
Refer to the Biosafety Manual Requirements Checklist available on
the CFIA website for
more details on the requirements to be included in the facility's Biosafety
Manual.
|
- Roles and responsibilities
- Conditions of access
- Orientation, security clearance, working alone/silent hours, medical.
- Training
- Supervision period, demonstrated capability, regulatory (WHMIS, etc.).
- Employee health and medical surveillance, if applicable
- Entry/exit
- Personnel (include non-routine scenarios such as emergencies and alarms),
materials, equipment, animals, and waste.
- Personal protective equipment
- Use, maintenance, decontamination.
- Transportation, handling and storage of pathogens
- Movement within the containment suite, inventory and access, receiving and
shipping.
- Decontamination and disinfection
- Disinfectant selection, use, shelf life daily procedures, special
considerations.
- Use of vaporized hydrogen peroxide, pass-through or decontamination
chamber.
- Use, maintenance and validation of approved decontamination systems
- Full room decontamination.
- Infection control practices
- Control of aerosols, prevention of injuries.
- Use of BSC/centrifuge/other.
- Hazardous waste management
- Segregation, storage and package.
- Autoclave procedures, incinerate, renderer.
- Housekeeping
- Animal care and safety
- Animal holding systems or tanks.
- Animal allergens, restraint mechanisms, proper handling techniques.
- Protocols for post-mortem areas, animal carcass movement and
transport.
- Emergency response
- Failures (HVAC, effluent
treatment system, power, BSC).
- Spills (biological – inside BSC, outside BSC, outside facility).
- Animal escape.
- Medical emergency within containment.
- Specific… earthquakes, flood, etc.
- Incident reporting
- Requirements/definitions.
|
- This section should be submitted in a separate binder.
- The list is not exhaustive and will change
depending on the facility and program.
- Please feel free to contact this office for more
information on the required components of an institutional biosafety program or
for specific procedure requirements.
|