| Item |
Required Information |
Notes / Suggestions |
| A. Contacts |
- Please provide name, title, fax and phone numbers of a key contact for
enquiries regarding the submission contents.
- Please provide current contact information for the institute director,
principal investigator (lab supervisor), facilities manager, and biosafety
officer.
|
|
| B. Program Intent |
- Give a brief overview of the agents to be used and procedures to be
followed in the facility, as well as the general goal/purpose of the work.
- Provide a list of pathogens and/or arthropods manipulated and/or stored in
the facility.
- A program change request must be sent to this office before any new
pathogen or arthropod is introduced in the facility, and anytime changes
related to the nature of the work or the procedures employed increase the risk
of pest escape from the facility.
- Please inform this office immediately before any significant change to the
procedures.
|
|
| C. Physical Layout |
- Provide a schematic of the facility identifying:
- Room and door numbers
- Purpose of each room
- Location of exhaust and supply air ducts
- Location of primary containment devices (e.g. BSC, etc.)
|
- Indicate the containment barrier on all drawings. Anteroom is typically
considered to be outside of containment.
|
| D. Verification & Performance Testing |
For each required test or verification, describe the test
procedure, acceptance criteria, observations, results, pass/fail decision,
names, dates, signatures, witnesses and corrective measures required. Testing
must have been performed during the last two years. |
|
| 1. Room Integrity |
- Visually and with a smoke pencil, or other visual aid, confirm the
integrity of all penetrations and seals on the containment perimeter (include
service penetrations and seals around doors, windows, and autoclaves).
- Visually inspect floors, walls, and ceiling for cracks, chips or wear, and
verify integrity of wall/floor and wall/ceiling joints.
- List all defects, corrective measures and re-test results.
|
- List by room, either in a table or schematic or by elevation of the
facility.
- All seals and joints should be periodically checked by smoke pencil or
other visual aid.
|
| 2. Communication Devices*
* Although this may not be a requirement in PPC-2A facilities, if the system is in
place, then testing should occur.
|
- Provide a list and a statement as to how they were verified as operational
(phone, fax, radio, etc.).
|
|
| 3. Self closing doors |
- List doors equipped with self-closing mechanism.
- Provide verification that self-closing devices operate as intended.
- Provide verification that lights automatically switch on/off with
opening/closing of doors.
|
- Lights in anteroom must automatically switch off when either door is
opened, and switch on only when both doors are closed.
|
| 4. Door Interlocks |
- Indicate combination of doors which are interlocked (e.g. door A with door B, door B with door A and
C).
- Verify operation of doors and applicable interlocks to ensure that doors
cannot be opened simultaneously.
- Verify that emergency egress overrides the interlocks.
- For facilities that do not have physically-interlocked doors, please
confirm that procedures are in place to ensure that no critical combinations of
doors can be opened simultaneously.
|
- Provide a plan of the facility and surroundings with clearly labelled doors
(i.e. each individual door is uniquely
identified).
|
| 5. Access Control and Security Devices |
- List access control and security devices on all entry points to the
PPC-2A facility (including
anterooms and emergency exits).
- Provide verification that devices operate as intended.
- If there is a door on the containment perimeter (e.g. equipment door, emergency exit), please
indicate of that door is sealed and how access is controlled.
|
- Verify that a correct code/card works and also that an incorrect code/card
will not work.
|
| 6. Ventilation and Inward Directional Airflow (during
normal operation) |
- If installed, provide verification of forced-air curtain at inner anteroom
door work as intended.
- Provide results of visual inspection of filters/screens installed on supply
and exhaust air duct for cracks, holes or wear, and verify integrity of seal
around filters/screens.
- Inward directional airflow to be visually demonstrated at all doors on the
containment perimeter (e.g. by holding a smoke
pencil, or other visual aid, at each door leading to adjacent area).
|
- Air must flow towards areas of higher containment.
- Provide a labeled plan with arrows indicating the directional airflow for
each door tested.
|
| 7. Waste Treatment |
- Provide results of validation tests for each waste treatment system (using
representative loads).
- Provide the time and temperature/concentration criteria required for the
decontamination of the specific agent/waste and references to supporting
literature.
- Provide a description of the different types of loads to be run and a short
description of the load test procedure (e.g.
laundry, solid waste, liquid waste, etc.).
- If used as a method of waste decontamination, autoclave must be verified
for operation as specified and must be microbiologically tested using
representative loads.
- Provide the time/temperature criteria required for the specific
agent/waste.
- Provide a description of the different types of loads to be run and a short
description of the load test procedure (e.g.
laundry, solid waste, liquid waste, etc.).
- Submit a time/temp chart and biological indicator test results for each
load test performed. Positive control results must be included (from the same
lot#).
|
- Generally, for technologies based on heat, Geobacillus
stearothermophilus spores are adequate and, for technologies based on
chemicals, Bacillus subtilis spores are used.
- Resistance of test organism must be representative of organisms likely to
be encountered.
|
| 8. Emergency Power System*
*Although this may not be a requirement in PPC-2A facilities, if the system is in
place, then testing should occur.
|
- Provide a load test report (previous monthly test report is
acceptable).
- Provide confirmation that all critical systems are on emergency power
(including, but not limited to, HVAC, lighting,
BSCs, essential equipment
and other safety system, etc.).
|
- Load testing results should verify that the emergency power system can pick
up and carry the load if required. When live load testing is not possible,
simulated load testing is acceptable.
|
| 9. Biological Safety Cabinets*
* Although this may not be a requirement in PPC-2A facilities, if the system is in
place, then testing should occur.
|
- Provide a list of all BSCs associated with the PPC-2A facility plus the test
certificate for each.
- Each BSC test
certificate must contain the following information:
- type of cabinet and type of exhaust connection;
- standard to which the cabinet was tested and the qualifications of the
tester;
- statement as to whether the HEPA filter was scanned or
probed, and the pass/fail criteria;
- when NSF 49 is
not applicable, the particle penetration given as a percentage of the upstream
challenge must be provided;
- indication of any repairs and retest results;
- downflow and inflow (exhaust) measurements and acceptable ranges specific
for the model;
- alarm test results - airflow tests, failure alarm test; and
- test of airflow patterns within the cabinet.
- Provide the calibration certificates for the equipment used for the
verification.
|
- This helps ensure all BSCs are accounted for.
|
| 10. Control Systems*
*Although this may not be a requirement in PPC-2A facilities, if the system is in
place, then testing should occur.
|
- Provide verification that supply and exhaust air systems are interlocked to
prevent sustained laboratory positive pressurization.
- Submit a report for each failure scenario performed.
- Failures to be simulated include:
- exhaust fan failure;
- supply fan failure;
- power failure (if not possible, provide reason why); and
- additional failures (as appropriate) for the particular facility (e.g. class II B2 BSC exhaust failure, control panel
failure, etc.).
- For each failure, verify that:
- room positive pressurization is prevented;
- inward directional airflow is maintained at all critical doors (verify the
airflow by smoke pencil, or other visual aid); and
- alarms function correctly to detect loss of containment.
- Control system performance verification should include speed of response,
accuracy, and repeatability.
- Each report to contain:
- description of the failure protocol and the control/HVAC system's
expected response;
- indication as to whether or not the system responded as expected;
- results of verification and maintenance of inward directional airflow;
and
- alarm results.
- Report and describe the investigation of any system failures (e.g. reversed airflow, fan interlock failure) as
well as corrective measures taken.
|
- In some circumstances brief airflow reversals (of a few seconds) may be
acceptable - consult with this office.
- A simple way to depict airflow results is with a labelled plan using arrows
to indicate the directional airflow at each critical door tested.
- Graphs and trend logs for failure scenarios are helpful and desirable.
|
| E. Biosafety Manual
Note: the Biosafety Manual is a critical part of the
certification documentation. Please realize that fulfilling the requirements of
this section entails a substantial amount of work and detail.
Do not leave this section until project completion.
An example of items to be address in each SOP are:
- Purpose
- References
- Personnel/Responsibility
- Glossary/Definitions
- Equipment and Material Required
- Safety
- Policy
- Detailed Instructions
Refer to the Biosafety Manual
Requirements Checklist for Plant Pest Containment Level 2
Facilities Handling Arthropods (PPC-2A) for more details on the
requirements to be included in the facility's Biosafety Manual.
|
- Roles and responsibilities
- Requirements/definitions
- Conditions of access
- Orientation, security clearance.
- Training
- Supervision period, demonstrated capability, regulatory (WHMIS, etc.).
- Entry/exit
- Personnel (include non-routine scenarios such as emergencies and alarms),
materials, equipment and waste.
- Personal protective equipment
- Use, maintenance, decontamination.
- Transportation, handling and storage of plant pests and arthropods
- Movement within the containment suite, inventory and access, receiving and
shipping.
- Decontamination and disinfection
- Disinfectant selection, use, shelf life daily procedures, special
considerations.
- Hazardous waste management
- Segregation, storage and package.
- Autoclave procedures, other methods.
- Housekeeping
- Emergency response
- Failures (HVAC, power, BSC).
- Spills (biological - inside BSC, outside BSC, soil, outside facility).
- Arthropod escape.
- Medical emergency within containment.
- Other… earthquakes, flood, etc.
- Incident reporting
|
- This section should be submitted in a separate binder.
- The list is not exhaustive and will change depending on the facility and
program.
- Please feel free to contact this office for more information on the
required components of an institutional biosafety program or for specific
procedure requirements.
|