Dairy Establishment Inspection Manual – Chapter 9 Good Manufacturing Practices
9.6 Satisfactory Inspections

This page is part of the Guidance Document Repository (GDR).

Looking for related documents?
Search for related documents in the Guidance Document Repository

Even if the GMP inspection is assessed as satisfactory the outstanding issues will still need to be noted on the CFIA/ACIA 950 form with agreed upon corrective action dates for all non-satisfactory tasks. As is the case with the indepth inspection the plant is required to submit corrective action dates even though the inspection may be considered satisfactory. The follow up to the correction would then be done on a subsequent GMP inspection. If the inspector so chooses he or she may want to request the establishment to respond in a letter outlining their intended plan of action which should be received no later than 3 weeks from the inspection date.